February 19 – China Yangtze Power Co., Ltd. (CYPC) announced its board's approval for the HouSihe Pumped Storage Power Station project in Gongyi City, Henan Province, with total investment capped at RMB 8.264 billion (USD 1.14B).
Project Specifications
Parameter | Value | Technical Significance |
---|---|---|
Installed Capacity | 1,200MW (4×300MW units) | Equivalent to 1.2 nuclear reactors |
Daily Generation | 6h full-load operation | 1.559B kWh annual output |
Cycle Efficiency | 75% | Industry-leading round-trip performance |
Unit Cost | RMB 5,896/kW | 12% below national average |
Strategic Timeline
-
2029 Q3: First unit synchronization
-
2030 Q2: Full commercial operation
Grid Stabilization Functions
► Peak shaving for 8GW renewable clusters
► Frequency regulation (±0.2Hz precision)
► Black start capability within 10 minutes
Capital Structure
-
Total Investment: RMB 8.264B
-
Equity Ratio: 20% (RMB 1.653B)
-
Debt Financing: RMB 6.611B (10-year loan at LPR-50bps)
Technical Highlights
-
Vertical single-stage Francis turbines (600rpm)
-
400kV GIS substation integration
-
AI-powered dispatch system
-
Market Context
-
China's 2025 pumped storage target: 62GW → Current capacity: 45GW
-
Henan Province renewable curtailment rate: 6.7% (2023) → Projected 3.2% post-2030
-